Long-needed infrastructure improvements and upgrades were recently made at Ingomar Middle School, the first since its original mid-1950s construction. A new 15,000-square-foot addition was constructed along with 100,000-square-feet of renovations. A new library, expanded art rooms and computer rooms, additional classrooms, and a new fitness/weight room were provided. Improvements also included new mechanical, electrical, air-conditioning, networking, and communications systems.

Pittsburgh, PA
15,000 SF New /
100,000 Renovation

more

Exterior improvements include updating the façade, new roof insulation, energy-efficient windows, and creating new entrances. To make Ingomar fully accessible, universal design techniques were utilized throughout.

Construction began in May of 2004 and was completed in August of 2005. Using phasing techniques, interruption to the educational process during construction was minimized.